|
Buyers have a wide range of options for resolving disputes with a supplier
or contractor. The choices are litigation, arbitration or one of the forms
of alternative dispute resolution such as mediation.
But they are not mutually exclusive. A dispute may first be referred to
mediation and then, if agreement is not reached within a defined time
scale, may be referred to arbitration. Only with construction contracts
as defined by Part II of the Housing Grant, Construction and Regeneration
Act 1996 must each party have the right to proceed to adjudication before
arbitration or litigation. So how do these methods compare?
Litigation is an adversarial action under procedural rules established
by statute and produces a legally binding decision (which sometimes may
be appealed to a higher court). But, despite reforms, litigation is still
complex and time consuming. As a result, costs are high - often more than
the value disputed - and judgements delayed. For example, an appeal was
allowed in April1996 in an action first heard in 1994 arising from events
in 1992. The case was simple and straightforward, involving no difficult
questions of law and the amount disputed was just over £4,000. The
costs must have been many times the sum, and it took four years from dispute
to final judgement.
The proceedings are public and, under the procedures for disclosure of
documents and cross-examination, matters may have to be revealed in court
which the plaintiff may prefer to keep secret. Costs are awarded against
the losing party.
Arbitration resembles litigation in that it is conducted under rules established
by statute and it results in a legally binding award enforceable in the
same way as a court judgement. However, the proceedings are in private
- so unwanted publicity is avoided - and the arbitrator is chosen by the
parties.
In the past, because the procedures adopted have been closely modelled
on the courts, the time taken and costs have also been similar. Now, under
the new Arbitration Act 1996 the parties and
arbitration tribunal have considerable procedural freedom and it is hoped
that both time and costs will be substantially reduced. As in litigation,
costs are usually awarded against the losing party.
Adjudication differs in that it is a process of expert determination.
The expert is appointed by agreement between the parties, either generally
or to decide a particular issue. Provided the expert keeps within the
terms of the appointment and does not show bias or act fraudulently, there
is no restriction on the way the decision can be reached. Unless constrained
by the terms of the appointment, there are no binding rules of evidence
- there need be no discovery of documents, oral submissions or cross examination
- and the expert can decide issues of law and fact. It is therefore both
quicker and cheaper than either litigation or arbitration.
If the contract provides for the expert determination to be final and
binding, a court will not interfere even if a mistake has been made -
unless the expert had gone outside the terms of appointment or acted fraudulently.
The expert does not have to give reasons for the decision unless required
to do so by the terms of the appointment.
The experts decision cannot be enforced as a judgement, but only
through an action for breach of contract. Unless the agreement provides
otherwise, there is also no power to award costs (usually divided equally
between the parties). Such powers, however, are proposed for adjudicators
of construction contracts under the Construction Act.
Alternative dispute resolution (ADR) is essentially a voluntary procedure
of structured negotiation under which the parties are led by a mediator
or conciliator to reach their own agreement on the dispute. The parties
are free to settle the details of the procedure to be followed and it
is essential that these are agreed at the outset. Non-contractual factors
such as the award of future business often feature in the settlement agreement.
It produces no decisions or award, but the agreement itself can be made
contractually binding and its breach enforced as a breach of contract.
Costs are usually shared equally. All depends on the willingness of the
parties to come rapidly to an agreement and on the mediators skill
in guiding them and removing the emotional factors that often blind parties
to their true advantage.
Which method should the buyer choose?
For construction contracts, both parties have the right to refer the dispute
to adjudication, so the real choice is between the subsequent arbitration
or litigation. With the new Arbitration Act, the advantage would seem
to lie along this route, although much depends on how the parties use
their freedom under the act and how well the new reforms to court procedure
work.
For other kinds of contracts, it is suggested there should be a first
step before recourse to arbitration or litigation. If the parties prefer
a continuing business relationship, then ADR is more attractive because
it avoids the win-lose syndrome. Even if the parties have not chosen ADR
in their contract, the court in commercial cases now often invites the
parties to take positive steps to set in motion ADR procedures.
If, however, either party actually wants someone else to make a decision
for them, or no future business between them is foreseen, then the dispute
should be referred to adjudication. As to whether the expert decision
should be final and binding, we suggest it should be binding on a particular
issue, but there should be a right of appeal on a general one.
SM
Peter Marsh and Frank Griffiths are associates at project strategy and
contract management consultancy FGA Ltd (0116 279 3383)
|